Job completed for Stan B
Completion date: April 13, 2023
Location: Muncie, IN
Solutions provided:
The installation team completed structural framing repairs to restore strength and stability to the affected area of the home. The work included replacement of 16 linear feet of damaged sill plate to reestablish a solid connection between the framing system and the foundation. In addition, twelve (12) sister joists were installed alongside the existing floor joists to reinforce weakened framing members and improve overall load distribution throughout the floor system. Each sister joist was properly aligned and secured to provide additional structural support and reduce floor deflection. Together, these repairs enhance the integrity and long-term performance of the floor framing system.
Team members on this project:
Celeo, Daniel